01What's inside
Built the way the work is done.
Portions
How the contract counts days, the notice period, and each separable portion's original and adjusted date for completion.
Register
A 200-row register of delay notices and EOT claims, with notice timing and status.
Holidays
Non-business days, for contracts that count EOT days in business days.
How to use
Instructions, and why days are never added across portions.
- Days claimed and granted are totalled per separable portion, never across portions.
- Each portion's adjusted date for completion moves with its own granted days, in calendar or business days.
- The notice due date is worked out from when you became aware of the delay and your contract's notice period.
- Notices are marked On time, Late, Not yet given or Overdue.
- Statuses from Notified and Claimed through Under assessment to Granted, Partly granted or Rejected.
- Days granted on a claim that isn't granted (or a grant without days) is flagged.
02How to use it
From blank to done in four steps.
- 1
Set the contract rules
Choose calendar or business days and enter the notice period from your contract (for example 28 days).
- 2
List the portions
Each separable portion with its original date for completion, or one row for the whole of the works.
- 3
Log delays early
Add the delay when you become aware of it; the notice due date appears and the clock is visible.
- 4
Record claims and decisions
Days claimed, then days granted and the decision. The portion's date for completion updates.
03Questions
Good to know.
When the spreadsheet stops scaling.
Palydin keeps delay notices and EOT claims in one register per contract, days tracked per separable portion, with every notice, claim and decision on the audit trail.
More free templates
- Progress claim templateA month-end progress claim: schedule of values, cumulative % complete, variations, retention, GST and the total payable, with the Security of Payment endorsement for your state.Get the template
- Payment schedule templateThe assessor's reply to a payment claim: claimed against scheduled amount line by line, a reason wherever they differ, retention, GST and the scheduled amount.Get the template
- Variation register templateEvery variation on the contract in one log: status, claimed and approved values, time impact and the adjusted contract sum.Get the template
- Risk register templateA 5×5 risk and opportunity register: likelihood and consequence scoring, bands, expected value, owners, treatments and a live heat map.Get the template
- Retention tracker templateRetention held claim by claim against the cap, releases at practical completion and the end of the defects liability period, and the balance still held.Get the template
- Cost report templateMonthly cost control by cost code: budget, approved changes, committed and actual cost, forecast to complete, forecast final cost and variance.Get the template